Construction update - May 28th

Our contractor, Ratcliff Consruction, has been working since May 1st on demo and prepping for the new infrastructure - HVAC, plumbing and bathrooms, electrical, stairway and ductwork. Construction should be complete within the next 13 months. 

 View the rest of today's pictures here

The former front entrance facing West Congress Street.
  
The hole in the ceiling is where the old stairway was.
Formerly the children's storytelling pit, temporarily a pond.  The cafe/vending area will overlook Mary's Garden and Live Oak Society member # 6140 LE LIVRE-CHENE DANS LE JARDIN DE MARIE
  
The new front entrance (in progress) will face Lafayette Street.
 

Thursday, May 09, 2013

Main Library construction - May 2013

The general contractor began on May 1st. The renovations are scheduled to take 14 months, with another 3 months for furniture, equipment, collection, and staff move-in. Here are pictures from the first week of the renovations. If the slide-show doesn't work (requires Flash), access the photos directly from this link